HGH Surgical Department building expansion

Hamad General Hospital – Doha, Qatar

As part of its overall expansion plans HMC proceeded with the construction of HGH surgery expansion department consisting of 20 new Operating Theatres.

UHS were subcontracted by Midmac Contracting company for the Medical Equipment Procurement Management Services that included tender award, management and coordination with suppliers, post award activities, site supervision works for testing, commissioning and handing over of the Medical Equipment.

 PM opens Integrated Surgery Centre at Hamad Hospital:
http://m.gulf-times.com/story/497529/PM-opens-Integrated-Surgery-Centre-at-Hamad-Hospital

1

 

 

 

March 2014
(Construction of slab in GF)

 

December 2014

 

 

 

December 2014
(Construction of architectural shell for Hybrid CT-ANGIO operation theatres)

 

3

 

 

 

March 2015
(Red-Marking for location of ceiling-suspended medical equipment, and preparation of floor trenches and provisions)

 

4

 

 

 

April 2015
(Installation of steel structures for medical equipment, and wall partitions)

 

5

 

 

 

May 2015
(Installation of in-floor rails for sliding CT)

 

6

 

 

 

May 2015
(Installation of ceiling suspended cable tray for sliding CT)

 

7

 

 

 

May 2015
(Installation of in-floor rail, and other architectural items)

 

8

 

 

 

July 2015
(Installation of X-Ray shielding protection (lead shielding)

 

9

 

 

 

August 2015
(Installation of Electro-Mechanical systems)

 

10

 

 

 

September 2015
(Installation of Laminar Air Flow system and room lights)

 

11

 

 

 

September 2015
(Finalizing provisions for surgical table, and floor self-leveling)

 

12

 

 

 

September 2015
(Installation of bracing and back-supports to hold wall-mounted medical equipment, and installation of in–wall cabinets)

 

13

 

 

 

October 2015
(Installation of wall glass-panels and lead-shielded door)

 

14

 

 

 

October 2015
(Installation of floor mounted column of surgical tables, 2nd fix of pendants, and ceiling tiles)

 

15

 

 

 

October 2015
(Installation of CT gantry)

 

16

 

 

 

November 2015
(Installation of floor vinyl, covering it with protection and installation of other MEP systems)

 

17

 

 

 

December 2015
(Installation of wall mounted medical equipment, and 2nd fix of surgical navigation system, surgical lights and others)

 

18

 

 

 

December 2015
(Removal of plastic covers and protections. Installation works have been completed)